Phase II

New Middle School Gymnasium - click for larger image
New Middle School Gymnasium

October 2012

 

       Site Work

       District Wide landscaping and restoration work

               

       High School

       Continue installation of masonry walls, mechanical, electrical and plumbing rough-ins at new Auditorium areas

       Begin corridor renovation

 

April 2012 - Phase II Project Schedule

       Site Work

       District Wide landscaping and restoration work

       Prepare restoration work at MS Gym and MS Link Addition

           

       Middle School

       Continue on Locker Room/Mod Team Room renovation work

       High School

       Continue installation of masonry walls at new Auditorium

       Begin erecting steel at new Auditorium

       Continue construction of 100 Wing Addition and Renovations


December, 2011

Progress and Schedule OverviewThe Phase II Capital Project is progressing nicely, on schedule and on budget. The project teams’ efforts have been, and continue, to be made easier by the exceptional spirit of cooperation from all of the staff, students and teachers of the district.

The site work contractor has completed the installation of all asphalt until next spring and was able to complete the installation of the underground storm piping and  structures at the Central Office Parking Lot, along with paving the lot and roadway to the bus loop. The site work contractor continues to install concrete sidewalks at the New Gym in preparation for the district to occupy the space in January. Details about the Grand Opening Celebration on Saturday, February 4 will be released soon!

During November, in the 100 Wing, contractors have installed windows, roof and exterior walls to create a water tight area to continue with installation of materials inside the building.

At the Auditorium area, foundations continue on schedule at approximately 70% complete, while the stage fly masonry walls were erected to 36’ high, or approximately half way.

In the new Gym addition at the Middle School, the finishes are being installed with the scoreboards completed and in the process of installing the wall pad, electrical finishes and the hardwood flooring.

The project team is also working on ongoing punch-list items throughout the building complex.


July, 2011
 
Summer construction in full swing
 
All parking lots and roads on the main campus will be under construction from June 27th until the start of school. Visitors to the campus will be directed to the Buffalo Road entrance and there will be one parking lot available. All visitors to the District Offices, High School, Middle School or Fairbanks Road Elementary should call ahead to find out where to enter and where to park for their visit.  This also includes any and all activities in the school buildings such as community education, meetings, and athletics. 

Major demolition of the High School Auditorium, Gym B, and classrooms in the 100-wing of the Senior High School began around the first of the month. All of these spaces will be offline and under construction throughout the summer and 2011-2012 school year. The Senior High School main entrance will be relocated to Door #4. 

Construction on the Middle School gymnasium, new classroom addition and link hallways will continue throughout the summer with the facilities slated to open in September.


 
May, 2011
 
Students leave their mark on construction project

Churchville-Chili Middle School students had the chance to leave their mark on the District’s $55.6  million capital improvement project on Wednesday, May 25th. About two dozen students, Superintendent Dr. Pamela Kissel, several administrators, faculty, physical education teachers, as well as several members of the Board of Education all signed a steel beam which will be used in the new Middle School Gymnasium which students will begin using January 2012.

“While the gym is the most visible part of the construction project, it is just the beginning of our three-year journey to transform our main campus so that our students have the kind of 21st century learning facilities they need and deserve,” said Assistant Superintendent for Business Services Frank Nardone.

 


 
December, 2010
 
Next Phase of Construction Begins at Middle School and High School

Churchville-Chili is ready to begin the next phase of construction as early as December 1, 2010 with the construction of a new Middle School Gymnasium, a two classroom addition at the High School, and a new Fitness Center at the High School. Click here to read the full story...

 


September, 2010

New York State approves construction plans

The District has received approval from the State Education Department to begin work on the next phase of the Capital Improvement project and the District is making preparations to start construction on or before December 1, 2010. Click here to read full story....
 
 

January, 2010

Next Phase of Construction Plans submitted to New York State while Sewer construction under way on Buffalo Road

Driving down Buffalo Road you can see that the sewer portion of the project, Phase II part 1, is nearly complete. The tie-in to the county line and pump station is finished and the District will be switching over to the new sewer system any day. Once the tie-in is complete and the system up and running, the old treatment plant will be decommissioned. Click here to read full story... 


 
June 16, 2009
 
There will be a lot of activity around the District over the summer connected to the Capital Improvement Project. Phase I is expected to be completed by this fall. The work for that Phase will focus on Fairbanks Road where the roof will be replaced and asbestos floors removed and replaced. That work will begin on June 29. Click here for full story...
 

 
December 9, 2008
 
Voters Approve $55,985,000 Capital Improvement Project: Phase II

Residents of the Churchville-Chili Central School approved Phase II of the Capital Improvement Project during a referendum vote Tuesday, December 9.  The $55,985,000 project will be funded through State Aid and the Capital Reserve Fund with no additional impact to the local tax share. Click here for full story...


December 4, 2008

Over the course of presenting the proposal for Phase II of the Capital Improvement Project, the same questions kept coming up. Click here for a list of frequently-asked-questions along with the answers.
 


October 15, 2008

The Churchville-Chili Central School District Board of Education approved a referendum vote for December 9, 2008 concerning Phase II of the Capital Improvement Project. The board held to their parameter of no additional impact on the local tax share. If approved, the $55,985,000 project would be funded through State Aid and the Capital Reserve Fund. Click here to read more...